Latest on Gungahlin roads - June 2017

Red car driving along road with signpost to nicholls ngunnawal

Construction continues on the duplication of Gundaroo Drive between Gungahlin Dr and Mirrabei Dr. Utility relocation and earthworks should be finished soon. Works then transfer to the widening of the existing carriageway. Expected completion in early 2018.

The first stage of Horse Park Drive duplication between Anthony Rolfe Ave and Well Station Dr is almost finished. These works include bridges over Gungaderra Creek, traffic lights on Mapleton Ave and reconfiguration of the signals at Wells Station Dr.

Works have also started on stage two of Horse Park Drive duplication between Anthony Rolfe Ave and Mulligans Flat Rd. For safety, traffic speeds will reduce during construction. Impacts on the pedestrian underpasses will be staggered for safe access under Horse Park Dr.