Construction of a new Canberra Institute of Technology campus in Woden commenced in 2022. The investment in a new purpose-built campus will feature a youth foyer and new public transport interchange for Woden. It will stimulate the local economy and support revitalisation of Canberra's southern hub. This project will have an ongoing and positive impact on the delivery of vocational education and training in the ACT.
Since beginning the build, monthly photos have captured progress at the construction site. Photos of enabling works, demolition of old buildings and construction of the new building are featured in the galleries.
Latest images
Released: 3 April 2024
Progress photo galleries
2024
During 2024 construction activities are focusing on:
- building the new Canberra Institute of Technology campus.
Progress photo galleries
2023
During 2023 construction activities focused on:
- enabling works at the construction site
- demolition of old bus interchange
- preparation of the construction site
- building the foundation for the new Canberra Institute of Technology campus.
2022
During 2022 construction activities focused on:
- demolition activities surrounding construction site
- construction of temporary bus interchange